Client : Global Top-3 insurer
headquartered in the UK
The client is among the leading insurance companies of the
world, created by the merger of two smaller UK insurance firms
in the mid 1990’s. The merged entity is a full-scale
insurance service provider covering all segments of insurance
activity, including both life and non-life.
As
part of its strategic long-term plan to maximize access to
high quality low-cost global information systems solution
providers, the firm established a relationship with VAST,
through VAST’s marketing agent in the UK. The relationship
envisaged the establishment of a development centre at VAST
with appropriate equipment and facilities, including a high-speed
communication link to the client’s offices in the UK.
VAST undertook the turnkey execution of the complete redesign
of the client’s Claims History Information System.
The
project involved the migration of fragmented Claims History
Data from a batch system using the older BDAM file management
system to a comprehensive DB2 based interactive system to
support the underwriting, Claims settlement and accounting
processing in the General Insurance Trade. Enhancements were
made to incorporate inquiries, reports, one-time and recurring
data loading and a transparent 3-layer interface to other
applications. Access Routines were developed to provide a
common seamless interface to access and manipulate data from
any application.
The
project consisted of onsite Project Planning, Requirements
Study, Analysis & Design phases, followed by development
and testing in India at VAST's Chennai center over a six month
period. The user acceptance and Implementation phases were
executed onsite at the customer's facilities, spread over
an eight-week period.
Since
the entire development phase of the project was carried out
and delivered from off-shore using a 64K link from Chennai,
project progress reviews and strategic meetings were conducted
on telephone and project reports were exchanged using e-mail,
using a standard monitoring and reporting procedure that was
specifically developed for the project.
Total
Project Effort 1000 Person days
Team Size 9 (peak)
Technical Environment
Hardware : IBM 3090 running MVS/XA
Software : COBOL, DB2, IMS/DB, MFS, RACF,
ENDEVOR
Location On-site – UK / Off-shore –
Chennai